Prep: AI Learning Day — Planning Meeting
Planning meeting: Tue Jul 7, 2026 Event date: Tue Jul 28, 2026 Owners/facilitators: Josh, Isabelle, Marlene, Gregory, Reuben Reuben’s role: Co-lead (with Josh) the three Flash Lab segments — Mapping Opportunities → Form Teams, Spark Gallery, Team Build Sprint. Also floats to support teams during the build.
Framing
A hands-on team day: moving the Accelerator team from consumers of AI to designers and operators of it. Three aims:
- Greater operational efficiency across the org
- Less busywork, more satisfying work
- Amplified impact of collective work
Working Agenda (as circulated)
| Time | Activity | Lead |
|---|---|---|
| 10:00–10:10 | Buffer / arrive + mingle | — |
| 10:10–10:25 (15m) | Welcome + Framing the Day | Josh, Isabelle, Marlene |
| 10:25–10:35 (10m) | AI 101: “AI or Not?” | Gregory |
| 10:35–10:50 (20m?) | Security & Data: the “Nutrition Label” | Josh + UIT |
| 11:00–11:30 (30m) | Flash Lab Pt 1: Mapping Opportunities → Form Teams | Josh & Reuben |
| 11:30–11:45 (15m) | Spark Gallery: What’s Possible | Josh & Reuben |
| 11:45–12:45 (60m) | Lunch | — |
| 12:45–1:25 (100m?) | Flash Lab: Team Build Sprint | Josh & Reuben (+Gregory float) |
| 1:30–2:00 (100m?) | Showcase — every team demos | — |
| 2:00–2:15 (15m) | Closing & Reflection: What Success Looks Like | Gregory & Marlene |
⚠️ Things to raise at the planning meeting
1. The schedule doesn’t add up — the Build Sprint is the casualty.
- “Team Build Sprint” is labeled 100 min but the slot (12:45–1:25) is only 40 min.
- “Showcase” is also labeled 100 min but the slot (1:30–2:00) is only 30 min.
- Those two “100 min” labels look like copy-paste artifacts. The real question: how long is the actual build? 40 min is very tight for teams to go from problem statement → working prototype with agents/vibe-coding. If the intent was ~100 min of build, the back half of the day needs a rethink (day currently ends 2:15).
2. Minor timing nits.
- Security & Data (10:35–10:50) is 15 min but labeled 20.
- There’s an unaccounted 10:50–11:00 gap before Flash Lab Pt 1.
3. Showcase capacity. “Every team demos” in 30 min — need a per-team time box once team count is known (e.g. 6 teams = ~4 min each incl. transitions).
4. Reuben/Josh division of labor across the three co-led segments isn’t split yet — worth agreeing who drives what (esp. Spark Gallery, which pulls from real Studio builds — Reuben has the deepest catalog here).
Spark Gallery — build candidates to pull from (Reuben’s)
(fill in at planning meeting — spans robust prototypes → scrappy one-offs to show range)
- Quick-builds catalog:
projects/quick-builds/
</content> </invoke>